Plaxton Bridge Progress

The team are making great progress to the construction works at Plaxton Bridge. At Plaxton we are constructing a 2.7mw Anaerobic Digestate plant. Ashcourt are operating as P/C and the main civils contractor for Solar 21.

To date, civils works have included; Excavation works that started in April 2019, 20,700T spoil removed from site to excavate to formation level. 4,440T + 6F2 chalk 1,500T type 1 used to form the sub-base and 2,380m3 of concrete poured to cast the base slab and bund walls and service yard slabs.