New Strata Homes Project Commences

We are pleased to have secured a new civils project for Strata Homes in Wawne, with Ashcourt being the principal contractor for the first 12 weeks. Works have already commenced this week and will finish in October 2022, totalling in a 33 week project of new roads and sewers in Hull.

The scope of works include a full compound set up, cut and fill using a GPS Komatsu D71 dozer, installation of a foul and 1350 surface water drainage. After this, the next phase of works will be to start on the new road formation.

Watch below how our 71PXi dozer, EC250 excavator and 922G Hydrema dumper work together to start the first phase of the project.