Works For Strata In Hull Progress

Works for Strata continue as we have recently seen the installation of the JV road through site, which has involved installing gullies, ducting and type 1 up to level to allow tarmac to be laid.

The kerb race machine also been to site to secure 370m2 of kerb race to enable us to start the block on edge. Other works include preparation for installing a new 1,350mm pipeline from site to the lagoon.